 |
 |
|
The Samaan Grove Wetland System |
Creating the Wetlands
by Kevin Kenny
Click images to enlarge
The large version of this diagram
opens in
a new window, allowing you to follow
the water flow as you read. > |
|
 |
The New Drainage System |
 |
 |
From the southeastern corner of the estate, waste water makes
its way down a newly constructed concrete drain (D1). Surface
water runoff from the estate's northern lots flows into the concrete
drain at the back of each property. |
 |
|
This drain ends at the silt trap. All of these silt traps were
designed to be easily cleaned using a backhoe. Although not installed
at the time of this report, there is a plan to place a litter
barrier just above the eastern trap to collect any floating debris
that washes down this drain. |
 |
|
Because most of the runoff currently comes from a pasture upstream
there is little trash in the drain at this point in time. From
here the water flows into the first of the constructed wetlands
(SWW#5). This wetland is only 1 metre (3 feet) deep and was planted
with rushes taken from the immediate area. It is the first natural
sediment trap for suspended solids and as such it is expected
to fill in, requiring cleaning and de-silting on a regular basis.
The initial design worked so well that, in the first high flow
situation, the entire bog filled up and had to be dug out and
replanted. |
|
From here the water then flows into Lake 1A (L1A) which is 4
metres (12 feet) deep and is meant to dramatically slow the flow
of water and allow some sediment to fall to the bottom. The water
next flows through a culvert located under the bridge (B1) or
through a self-leveling pipe buried deep under the road at a
depth of about 3.5 metres (10 feet). The self-leveling pipes
were installed under both bridges to ensure that, when the level
of the lake falls below the culvert, both sides of the Lakes
1A-1B and Lakes 2A-2B are always at the same level. |
 |
< Lake 1A soon after completion
and a year later, after it
had settled and the waterlilies had started to grow. > |
 |
|
The land beside Lake 1B hosts one of the signature samaan trees
from which the development takes its name. From here the water
passes into the second wetland (SWW#6) flowing through a 15 centimetre
(6 inch) PVC pipe. The height of the pipe is set to keep water
flowing into the wetland throughout the year. In times of flood
the water will flow over the spillway completely bypassing the
wetland system. The photograph below left shows soap suds at
the end of the spillway indicating the level of nitrates and
phosphates contained in the water. |

Samanea saman |
 |
 |
|
The volume of water flowing into SWW#6 can be adjusted by changing
the height of the inlet in the supply pond L1B, above right.
We continue to experiment with the water flow as the objective
is to always have water flowing through the wetland even during
the driest months of the year. |
 |
< This shows wetland SWW#6A when it
was first constructed --
-- and one year later. This
pond was planted with Vallisnaria which now covers 60% of its
bottom. > |
 |
|
Next the water flows down an earthen drain into the second section
of wetland SWW#6B. This bog has a wide range of plants growing
on a shelf that was built on the northern side of the pond. The
shelf was sealed with clay and covered with 15 centimetres (6
inches) of topsoil to speed up the growth of the plants. During
the rainy season this shelf is covered by a foot of water. It
was designed to grow a host of different bog plants meant to
create a diverse habitat. Although only a year and a half old,
black-belly tree ducks and the common gallinules have been observed
with young in this area. The bog is one of the most beautiful
as it winds its way down to the second lake system L2. |

SWW#6B in its first year, just before it was
filled
with water |

Because there was not enough water coming
into the system we had to pump water from Lake 2B the first year. |
|
Water flows into Lake 2B, then down the spillway into an earthen
drain which goes through the estate. |

Spillway from SWW#6 to Lake 2B |
 |

^ Spillway from
Lake 2B > |
 |
|
Construction of the Lakes |
|
One of the main challenges in constructing ponds on the estate
is the hard coral surface that exists in many places. When EDSA,
the landscape architects, laid out the lakes they did not know
the exact boundaries or structure of the coral formations. As
the project progressed we found that coral formations would dictate
the placement, dimensions, depth and size of many of the ponds.
It became far too expensive to consider using mechanical equipment
to place them in the exact spot where the landscape architect
wanted them to go. |

Pond carved from hard coral |
|
A good example is the pond shown above which was dug out of an
area containing hard coral. Had we known the soil condition before
we sold the land we would not have placed this pond in this location.
However, because of the commitment made to the customer we ended
up digging the pond in the coral base as agreed. We also experienced
problems with water levels in L1 and SWW#6 because the excavated
coral sections were not properly lined with clay and leaked.
|
|
The Wells
Another challenge we faced in the early design of the project
was how to deal with periods of severe drought, which would result
in reduced water flow through the wetland system. During the
dry season wild fires burn many areas of the estate. Since the
main purpose of the developed wetland was to improve the quality
of surface runoff flowing all year round we had to find a way
to keep the wetland productive.
We decided to develop a series of wells located at strategic
points which would be used to supply water to the drains feeding
the wetlands. It was a bonus that we subsequently found a spring
at Samaan II. |
|
This photograph illustrates the problem at SWW#6. The waterlilies
were high and dry in May 2005 after the first dry season. Most
of them and most of the bog plants survived this condition and
were flourishing in July when the water level returned to normal. |

Canaan Village drain |
Canaan Drain (D2)
A main drain that flowed through the estate came off of the
Cannan Feeder Road south of the development. This drain carried
the bulk of the liquid waste from Canaan village. We built a
silt trap and trash barrier which are checked and cleaned frequently.
We fenced the silt trap to protect children from the village,
who were seen playing and catching fish in the trap area. This
water flows through another new concrete drain at the back of
the southern boundary wall of Samaan II, down through a series
of steps and into Lake 2A. |

Silt trap and drain |

Silt trap T2 |

Step drain |

Trash barrier |
As the water enters Lake 2A it flows
through some coral rubble placed to
prevent erosion. |

Lake 2A
These two photographs were taken one year apart.
The beautiful Samaan tree at the right is one of the
largest found growing on this part of the estate and
every effort was made to preserve it. |
 |
|
Next the water flows through a culvert under the second bridge
(B2). As with B1 we installed a self-leveling pipe. From there
water flows into Lake 2B, then down a spillway into an earthen
drain. There was no coral encountered in constructing these two
lakes and all the sides and bottom were sealed with clay found
on the site.
Lake 2B when first constructed
> |
 |
|
Samaan II
To our delight we found a natural spring when we started clearing
the 2.4 hectare (6.6 acre) site known as Samaan II. We had the
water tested and were surprised at the high quality. This allowed
us to create another very different lake (L0). The spring produces
160,000 liters (40,000 gallons) per day during the rainy season
but falls off by the end of the dry season to around 41,000 liters
or 10,000 gallons per day. There is no silt entering this lake,
making it one of the clearest on the development. |
|

Spring on Samaan II |

|
|
The first thing we had to determine was the dimensions of the
lake, which were defined by a layer of hard coral on the southern
boundary. A number of trial holes were dug and we found that
there was a wall of hard coral directly under the proposed road.
All the other soil had a high component of clay. |
 |

Test hole |

Starting the lake |

Construction drain for spring water |

Cutting the coral drain |

Building the drain in the coral |

Shelves on the eastern side |

Pumping the lake during construction |

Cutting the shelf in the clay on the west
side |

The north side near the drain |
 |
< Lining the lake
with coral > |
 |
|
We started the excavation by draining the existing pond. The
coral shelf on the western or right side of the pond was left
quite steep while on the eastern and northern sides the slope
was more gradual as it consisted of clay. We did not line the
coral with clay since we wanted the spring water to flow unimpeded
into the pond. It was interesting to see that most of the water
flowed into the new lake from the south coral shelf just below
the point where we constructed the drain under the road. |

Lake 0 finished |
|
The height of the water table was just 60 centimetres (24 inches)
below the level of the road. One of the challenges during construction
was the heavy ground water flow which required continuous pumping.
We built a number of shelves on both sides of the pond which
in time will be planted with submersed grasses meant to attract
wildlife both above and below the water. |
|
Maintenance
We had to develop maintenance practices that would keep the
ponds, lakes and wetlands looking beautiful all year long. Already
there are some interesting lessons learnt. |
|
|
The first is that certain plants are more aggressive than others
and will quickly crowd out the less aggressive species. There
are some terrestrial plants that will thrive in wet areas and
smother the bog plants. One of these is a water grass (above
right) which grows on the sides of drains and ditches. The second
is Ipomoea aquatica, a vine locally called "wild
potato" (perhaps because it looks similar to the local sweet
potato vine) which spreads quickly and will cover the entire
pond if left unchecked. |
|

< ^ Ipomoea aquatica |
|
The direction of the wind with respect to the surface water
is something that needs to be considered in lake and pond design.
All floating debris is pushed towards the leeward side of the
lake. In an ideal world the outfall of this lake should also
be at the leeward corner making the collection of floating matter
easy. Wind will also destroy water lily pads. Victoria amazonica
was planted down wind in lake 2A and we often found the pads
flipped over and covered with floating debris which had been
pushed on to the top of the leaves, eventually causing them to
rot.
Trash barriers on all drains feeding the ponds and lakes are
essential for the easy maintenance of the lakes. We now have
someone constantly working on the maintenance of the entire wetland
system. |
 |

< Victoria surrounded by trash | ^ Worker
cleans it out |
|
When new ponds are lined with clay there is little nutrient
in the soil and the plants need to be fertilized during their
first year. In the early days, fertilizing with pond tabs was
essential in making the water garden attractive. As the pond
matures and collects silt it will eventually sustain itself.
During the initial planting period we use no fertilizer for
about one month to allow the roots to grow. Once the plants have
become established, we fertilize once a month during the first
year to produce good results. The size of the leaf and the flowering
rate of the plant is usually a good indicator of when to fertilize.
In our case, one of the main reasons we built the wetlands was
to remove nutrients from the water, so the use of fertilizer
is controlled and limited. There are all sorts of application
rates for pond tabs. For small plants we use two tabs per plant
placed about 10 centimetres (4 inches) from the root base. With
more mature plants we use up to 10 tablets placed about 1.5 metres
(5 feet) from the base of the main stems. The root base can become quite
large with older plants and we have difficulty finding soil in
which to place the tablets. We simply push a finger between the
roots placing the tablets among the roots and then cover the
hole with clay. Check Victoria-Adventure
for additional advice on fertilizing. |
|
|
Previous Page | Next Page
Introduction &
Index
WGI ONLINE
Journal Table
of Contents
|